Published DateTime Event Start DateTime Event End DateTime Unavailability Type Available Capacity (MW) Affected Unit Reason for Unavailability Event Status
02/07/2019 14:22:35 06/04/2023 16:13:28 26/06/2023 10:25:30 Planned 0 DRAXX-2 Planned Outage Active
02/07/2019 14:18:28 05/05/2022 16:14:28 16/06/2022 13:25:30 Planned 0 DRAXX-6 Planned Outage Active
02/07/2019 14:16:49 23/06/2022 16:13:28 12/09/2022 10:25:30 Planned 0 DRAXX-4 Planned Outage Active
02/07/2019 14:05:06 29/07/2021 16:11:58 04/11/2021 13:28:30 Planned 0 DRAXX-1 Planned Outage Active
27/01/2019 15:14:02 26/04/2020 23:00:00 22/05/2020 23:00:00 Planned 0 RYHPS-1 Planned Outage/Restriction Active
31/12/2018 13:47:10 31/07/2021 22:47:05 19/08/2021 01:06:00 Planned 0 DAMC-1 Planned Outage/Restriction Active
31/12/2018 13:43:35 29/06/2020 04:29:47 12/07/2020 16:00:12 Planned 0 CRUA-3 Planned Outage/Restriction Active
31/12/2018 13:42:26 15/06/2020 04:29:45 28/06/2020 16:00:15 Planned 0 CRUA-2 Planned Outage/Restriction Active
31/12/2018 13:35:52 02/03/2020 04:29:45 15/03/2020 16:00:15 Planned 0 CRUA-1 Planned Outage/Restriction Active
21/12/2018 14:45:17 06/04/2023 16:14:28 18/05/2023 13:25:30 Planned 0 DRAXX-4 Planned Outage Active