Unit Availability

Unit Availability

This website is the backup source for REMIT information in relation to Drax Group's units. The primary source is the Elexon BMRS website.

to



All parameters in the More Filters are OPTIONAL



For information regarding Drax outage events prior to 13/12/2015 please visit the Historic MEL page.

Published DateTime Event Start DateTime Event End DateTime Unavailability Type Available Capacity (MW) Affected Unit Reason for Unavailability Event Status
16/01/2024 06:36:53 13/07/2024 03:13:29 13/07/2024 18:57:10 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:02:57 09/03/2024 03:13:29 09/03/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:03:53 16/03/2024 03:13:29 16/03/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:04:41 23/03/2024 03:13:29 23/03/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:06:24 30/03/2024 03:13:29 30/03/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:09:20 06/04/2024 03:13:29 06/04/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:09:20 13/04/2024 03:13:29 13/04/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:11:15 20/04/2024 03:13:29 20/04/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:12:16 27/04/2024 03:13:29 27/04/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:19:06 11/05/2024 03:13:29 11/05/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:22:41 08/06/2024 03:13:29 08/06/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:25:23 15/06/2024 03:13:29 15/06/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:26:13 22/06/2024 03:13:29 22/06/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:27:01 29/06/2024 03:13:29 29/06/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
16/01/2024 12:28:54 06/07/2024 03:13:29 06/07/2024 18:51:30 Planned 0 DRAXX-4 Boiler / Fuel Supply Active
23/02/2024 00:00:50 19/02/2024 12:34:47 07/03/2024 05:00:00 Unplanned 25 DRAXX-12G Boiler / Fuel Supply Active
22/02/2024 18:06:52 27/02/2024 05:00:00 27/02/2024 05:30:00 Planned 0 CRUA-1 Draft Tube Gate Lowering Conditions Active
22/02/2024 18:08:30 27/02/2024 15:00:00 27/02/2024 15:30:00 Planned 0 CRUA-1 Draft Tube Gate Lowering Conditions Active
22/02/2024 18:19:00 27/02/2024 05:00:00 27/02/2024 05:30:00 Planned 0 CRUA-3 Draft Tube Gate Lowering Conditions Active
22/02/2024 18:20:49 27/02/2024 15:00:00 27/02/2024 15:30:00 Planned 0 CRUA-3 Draft Tube Gate Lowering Conditions Active
25/01/2024 11:19:07 04/05/2024 07:41:58 04/05/2024 15:26:00 Planned 0 DRAXX-1 Electrical System Active
25/01/2024 11:20:47 04/05/2024 09:08:28 04/05/2024 13:24:30 Planned 0 DRAXX-2 Electrical System Active
25/01/2024 11:22:17 04/05/2024 09:08:28 04/05/2024 13:24:30 Planned 0 DRAXX-3 Electrical System Active
25/01/2024 11:23:37 04/05/2024 09:54:00 04/05/2024 12:01:00 Planned 0 DRAXX-9G Electrical System Active
25/01/2024 11:24:41 04/05/2024 09:54:00 04/05/2024 12:01:00 Planned 0 DRAXX-10G Electrical System Active

Items per page:

Page 2 of 3

Last publication made: 23/02/2024 00:00:50

All times quoted within the message detail are shown in UK Local Time